HEA Update – Friday 2:30pm

| December 28, 2012 | 0 Comments

by Joe Gallagher

HEA Banner

Homer Electric Association crews continue to make progress in restoring power to the Seldovia area.

Thursday evening crews energized the line from Seldovia to Six Mile Jakolof Bay Road. Today, the crew was able to bring power to the 52 meters between Six Mile and Jakolof Bay.

HEA crews are now concentrating their efforts on locating and repairing a problem on the main line between Big Tutka Bay and Little Tutka Bay.

Seldovia, Port Graham, and Nanwalek will continue to be served by the Gerry Willard Generation Plant in Seldovia  and the generator in Port Graham until repairs are completed in the Big Tutka Bay area.